The residential building at Nussbaumstrasse 18 was extensively renovated and two wooden attic floors were added. Timbatec was responsible for the structural design of the extension and supported the project as a timber construction engineer.

Facts and images
Construction Data
Involved
Addition under construction from a drone's perspective
Addition under construction from a drone's perspective
Prefabricated modules are brought to the construction site
Prefabricated modules are brought to the construction site
Installation of floor elements
Installation of floor elements
direct connection to the existing buildings
direct connection to the existing buildings

The project
In a central location in Zurich's Kreis 3 district, the existing residential building at Nussbaumstrasse 18 is undergoing comprehensive renovation and will be extended with two additional attic floors in timber construction. The extension will create new, contemporary living space, while the floor plans on the existing floors will be adapted to meet today's requirements. The new gable roof connects to the existing hipped roofs of the neighboring buildings and blends harmoniously into the urban environment.

The construction method
The floor of the extension consists of horizontal glulam elements spanned between steel beams, through which the loads are transferred directly into the existing structure. The elevator shaft was constructed as a prefabricated, enclosed CLT shaft and placed in one piece on top of the existing concrete core. The roof was constructed using prefabricated elements.

The challenge
The existing hipped roofs had to be extended to form continuous gabled roofs. The transitions were particularly challenging, as the connections to the fire walls had to be precisely executed and the fire barrier secured.

Construction costs

- Total costs BKP 1-9: CHF 5.6 million

- Building costs BKP 2: CHF 5.3 million

- Timber construction BKP 214: CHF 560'000


Services of Timbatec

- SIA Phase 31 Preliminary design

- SIA Phase 32 Construction project

- SIA Phase 41 Tendering and comparison of bids

- SIA Phase 51 Implementation project

- SIA Phase 52 Execution

Client
arc Architekten AG
8045 Zürich


Timber construction
Köfler Holzbau
8909 Zwillikon


Photography
Tom Licht Photography
8048 Zürich


Insta: tomlicht_arch_photography
Privacy notice
This website uses external components that can be used to collect data about your behavior. Read more about this in our privacy policy.