Expansion of the Loogarten Foundation Care Center, Esslingen

2025

The Loogarten Care Center in Esslingen was expanded by two stories using innovative TS3 technology in a short period of time, without interrupting operations, using locally sourced wood, thereby doubling its capacity.

Facts and images
Construction Data
Involved
A completed resident's room before it is furnished.
A completed resident's room before it is furnished.
Visualization of a two-story addition to the existing floor plan. Columns, slabs, finished
Visualization of a two-story addition to the existing floor plan. Columns, slabs, finished
CLT panel prepared along its long side being erected prior to TS3 joint grouting.
CLT panel prepared along its long side being erected prior to TS3 joint grouting.
The TS3 joint sealant is applied on-site during installation.
The TS3 joint sealant is applied on-site during installation.
Floor slab details (left: exterior wall with facade connection) and (right: interior wall inside the building).
Floor slab details (left: exterior wall with facade connection) and (right: interior wall inside the building).

The project
For this two-story addition, Timbatec was responsible for the fire protection, structural engineering, and building physics aspects of the project. The requirements for the construction project were diverse and demanding: The use of TS3 technology, fire protection solutions with encapsulated cross-laminated timber (CLT) floors and walls, as well as fulfilling the client’s request to source the approximately 2,000 m3 of wood required from the forests of the surrounding municipalities of Küsnacht, Erlenbach, Herrliberg, and Egg. This required a three-part tender for the forestry operation (timber procurement), the timber industry (sawing and further processing), and the timber builder—a collaboration that combined technology, logistics, and regionality.

The construction method
TS3 technology was used for the addition, in which cross-laminated timber panels are bonded lengthwise and end-to-end with cast resin. This creates solid, biaxially load-bearing floor slabs that transfer loads precisely and efficiently to the load-bearing walls and columns of the existing solid-construction floors—this construction method is characterized by its high load-bearing capacity and enables slender timber structures.

The challenge
The use of locally sourced wood required separate bids from the forestry department, the wood processing industry, and the timber contractor (generally involving slightly more planning effort). On-site, enclosed timber components in the areas where ceiling joints meet had to be modified to meet fire safety requirements.

Construction Data

- 2 new additional floors

- Gross floor area: 1500 m2

- Cross laminated timber: 860 m3 (iincluding interior walls)

- TS3-ceilings 2500 m2

- TS3-Technology: 1000 lm joint

- Glued laminated timber (glulam) 70 m3

- Exterior wall elements 1100 m2


Construction costs

- Timber construction CHF 2.3 million


Services of Timbatec

- SIA Phase 31 Preliminary design

- SIA Phase 32 Construction project

- SIA Phase 41 Tendering and comparison of offers

- SIA Phase 51 Implementation project

- SIA Phase 52 Execution

- SIA Phase 53 Commissioning

Architect
asa AG
8640 Rapperswil


Client
ARGE Loogarten
8610 Uster


Timber construction
Kübler Holzbau AG
8618 Oetwil am See


Others
Schilliger Holz AG
6403 Küssnacht am Rigi


Construction management
Reichle Architekten AG
8610 Uster


Privacy notice
This website uses external components that can be used to collect data about your behavior. Read more about this in our privacy policy.